Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 15, 2019 - 20:00 PDT
Scheduled
Fiber optic circuits cutovers are scheduled for the week of April 15th-19th. The work will be done in the evenings, 8PM to 4AM.
The cut over consists of a total of 45 fiber optic circuits in 3-5 evenings. A subset of them are the Health circuits listed below and will be migrated on the 16th: