Network Maintenance: reload network switch wan-ljpro-b226-b227-som-c9300-48 on Thursday, Oct 1, 2026 between 3 AM and 5:30 AM

Scheduled Maintenance Report for ITS Network & Systems

Completed

The scheduled maintenance has been completed.
Posted Oct 01, 2026 - 05:31 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 01, 2026 - 03:00 PDT

Scheduled

Datacom/Netmon have scheduled the following network maintennce:

What: reload network switch wan-ljpro-b226-b227-som-c9300-48
When: Thursday, Oct 1, 2026 between 3 AM and 5:30 AM
Scope: reload the switch to upgrade it to the current standard IOS software code
Impact: loss of wired and wireless connectivity to the switch for approx 30 minutes.
The switch is located at La Jolla Professional Bldg suite B226-227 - DR FRANK
Posted Sep 26, 2026 - 13:11 PDT
This scheduled maintenance affected: Network.