Network Maintenance: Reload network switch sio-igpp-munk-0-1-flr3-c9300-stk on Wednesday April 16, 2025 between 3 AM and 5:30 AM

Scheduled Maintenance Report for ITS Network & Systems

Completed

The scheduled maintenance has been completed.
Posted Apr 16, 2025 - 05:30 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 16, 2025 - 03:00 PDT

Scheduled

Datacom/Netmon has scheduled the following maintenance:

What: Reload network switch sio-igpp-munk-0-1-flr3-c9300-stk
When: Wednesday April 16, 2025 between 3 AM and 5:30 AM
Scope: reload the switch to upgrade the IOS software code from an old version to the current standard software code.
Impact: Loss of wired and wireless connections to network switch sio-igpp-munk-0-1-flr3-c9300-stk for approx 30 minutes.
The switch is located at igpp sio munk lab.
Posted Apr 12, 2025 - 11:17 PDT
This scheduled maintenance affected: Network.