Reload rsnt-erc-msa-vrde-n-3750-stk network switch #2 of the stack.

Scheduled Maintenance Report for ITS Network & Systems

Completed

The scheduled maintenance has been completed.
Posted Oct 11, 2019 - 05:00 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 11, 2019 - 04:00 PDT

Scheduled

WHAT: Reload rsnt-erc-msa-vrde-n-3750-stk network switch #2 of the stack.
WHEN: Friday 10/11/19 4:00 AM
SCOPE: Reloading switch 2 of the stack to fix stacking/priority issue.
IMPACT: Loss of wired and wireless network connectivity to devices connected to rsnt-erc-msa-vrde-n-3750-stk switch #2 only, other switches in the stack will not be impacted.
Posted Oct 09, 2019 - 12:10 PDT
This scheduled maintenance affected: Network.