Network Maintenance: reload network switches n-rgrf-1-1-9300-stk, n-rgrf-2-1-9300-stk, and n-cnt-3-1-c9300-stk on Thursday, March 12, 2026 between 3 AM and 5:30 AM

Scheduled Maintenance Report for ITS Network & Systems

Completed

The scheduled maintenance has been completed.
Posted Mar 12, 2026 - 05:30 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 12, 2026 - 03:00 PDT

Scheduled

Datacom/Netmon has scheduled the following network maintenance:

What: reload network switches n-rgrf-1-1-9300-stk, n-rgrf-2-1-9300-stk, and n-cnt-3-1-c9300-stk.
When: Thursday March 12, 2026 between 3 AM and 5:30 AM
Scope: reload each switch to upgrade it to the current standard software IOS code.
Impact: loss of wired and wireless connectivity to network switches n-rgrf-1-1-9300-stk, n-rgrf-2-1-9300-stk, and n-cnt-3-1-c9300-stk for approx 30 minutes for each switch.

n-rgrf-1-1-9300-stk     Location: Shiley RGRF TR 1.1 9405 Campus Pt Dr  
n-rgrf-2-1-9300-stk    Location: Shiley RGRF TR 2.1 9405 Campus Pt Dr  
n-cnt-3-1-c9300-stk  Location: Center for Novell Therapeutics TR3.1
Posted Mar 10, 2026 - 10:58 PDT
This scheduled maintenance affected: Network.