Fiber Link [socsci-4-1-3850-48 (Te1/1/3 SFP-10G-LRM)<------------>(SFP-10G-LRM Te1/11) socsci-1-1-4500x-dist SFP-10G-LRM]
Scheduled Maintenance Report for ITS Network & Systems
Completed
The scheduled maintenance has been completed.
Posted Jul 02, 2021 - 08:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 02, 2021 - 07:00 PDT
Scheduled
WHAT: Fiber Link [socsci-4-1-3850-48 (Te1/1/3 SFP-10G-LRM)(SFP-10G-LRM Te1/11) socsci-1-1-4500x-dist SFP-10G-LRM]

WHEN: Friday, July 2, 2021 at 7 AM – 8 AM

SCOPE: Clean fiber and replace optic to resolve connectivity issues.

IMPACT: Loss of wired and wireless network connectivity to network switch socsci-4-1-3850-48 for approx 60 minutes.
Posted Jun 30, 2021 - 13:29 PDT
This scheduled maintenance affected: Network.