Agg-vss2- Campus Backbone Router upgrade
Scheduled Maintenance Report for ITS Network & Systems
Completed
The scheduled maintenance has been completed.
Posted Nov 09, 2024 - 08:00 PST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 09, 2024 - 05:00 PST
Scheduled
ITS has scheduled the following maintenance:

START: Saturday, November 9 from 5:00 A.M
STOP: Saturday, November 9 from 8:00 A.M

IMPACT: During this window there will be intermittent outages to all wired and wireless campus networks

1) Node-b including: Book Store, Canyon View, Canyon Vista, Chancelor Complex, CMRR (Center for Magnetic Recording Research), DIB (Design and Innovation Building), foodworx, Geisel Library, Gilman Parking, HDH Sixth Launday, Literature Building, Music Center, North Campus Facilities Management Substation, Pepper Canyon Hall, Price Center, Price Center Expansion, VISUAL ARTS BUILDING, Warren Student Activity Center , wlh (Warren lecture Hall), Warren Black Facility Management FM, Warren Brennen FM, Warren Douglas FM, Warren Goldberg FM, Warren mall outdoor Classroom

2) Node S: (Career Services, Center Hall, SSC Student Services Complex, Student Health.

3) Node G: (La jolla Pro)

4) Engineering (bioengineering), calit (Atkinson Hall), ebu1 (Jacobs School of Engineering), serf, smeb, ebu2 , ebu3 (Computer Science and Engineering)

5) [sdsc]cui-sherlock and [sdsc]CIOPS-MGMT-VMOTION

Please contact ITS Service Desk at (858)246-HELP(4357) or servicedesk@ucsd.edu if you have any questions or concerns.
Posted Nov 06, 2024 - 09:39 PST
This scheduled maintenance affected: Network.